Keeyask Generating Station

In 2013, through a publicly advertised and competitive process, Chant was selected by Manitoba Hydro to prepare an independent AACE Class 2 contractor style capital cost estimate for the Keeyask Project and provide feedback on proposed risk transfer strategies, specific contract language and overall constructability of the works.

 

Scope of Work:
  • Conducted a constructability review on each major aspect to determine the most efficient means and methods of construction
  • Incorporated these construction methodologies into the direct cost estimate
  • Thoroughly developed project indirect costs and plant items to ensure all aspects of the construction process were included in the cost estimate
  • Completed a comprehensive risk analysis to support Manitoba Hydro’s overall project risk assessment effort

LOCATION / Manitoba, Canada CLIENT / Manitoba Hydro STATUS / Complete YEAR / 2013 PROJECT VALUE / $1.4 Billion